S-NEM2300-bus Benchmark Model

Overview

Synthetic grid model of the Australian National Electricity Market (NEM) power system.

The SNEM2300-bus benchmark system is a large-scale, real-time EMT compatible model that has a topology and characteristics similar to those of the original longitudinal Australian National Electricity Market (NEM) power system. It comprises 2340 buses, 196 synchronous generators with their corresponding control schemes, 1790 transmission lines, 1696 dynamic loads, and 1531 transformers, among other power system components.

Key Features

  • First synthetic EMT grid with longitudinal structure/topology.
  • Testbed suitable for frequency, voltage and transient stability studies, and integration of inverter-based generation/load.

Getting Started

  1. Open the benchmark model in HYPERSIM
  2. Analyze the system
  3. Generate code
  4. Start simulation
  5. Use the model as a benchmark for different power system studies/analyses

Model Specifications

Parameter Value
Product HYPERSIM
Simulation type Offline
Application Energy
Model file S-NEM2300-bus Benchmark.zip
Recommended time step 50 us
Known limitations Compatibility: Real-time EMT compatible model.
Modelling: DC links represented as voltage sources at each end.
Graphical: Connection of components, wires, present graphical overlaps.

Downloads

Do you run it using ephasorsim ?

Hi @Vincent_Jiang, the model was developed for HYPERSIM.